# Heavy Machinery Deployed Between Sodala And Gurjar Ki Thadi For Road Widening As Traders Demand Compensation

> Enforcement teams initiated a major clearance drive along New Sanganer Road to expand it to 160 feet under court directives, triggering protests from local shopkeepers seeking financial relief.

**Type:** article · **Category:** Rajasthan · **Published:** 2026-10-05 · **Source:** TrendKia
**Canonical:** https://trendkia.com/en/rajasthan/sodala-se-gurjar-ki-thadi-taka-saraka-chauri-karane-pahunchi-bhari-mashinen-muavaje-ki-manga-para-are-dukanadara-42979 · **Language:** English
**Tags:** Jaipur, New Sanganer Road, JDA, Road Widening, Demolition Drive, Compensation Protest

A large scale administrative drive commenced along New Sanganer Road in Jaipur on Monday to facilitate crucial road widening work. Acting on judicial directives, enforcement squads from the development authority initiated the removal of structures along the stretch extending from Sodala intersection to Gurjar Ki Thadi. A substantial police contingent was deployed across the area to preserve public order during the exercise, supported by approximately two dozen bulldozers and poclain machines deployed to dismantle obstructions. Dumpers and tractors were also pressed into service to clear the resulting debris immediately from the site.

## Targeting A 160 Foot Width Following Advance Notice
The urban widening initiative aims to expand New Sanganer Road to a width of roughly 160 feet. At present, several sections along this arterial corridor measure merely 100 to 120 feet wide, creating frequent vehicular bottlenecks. Prior to initiating on ground action, the authority had carried out demarcation surveys to identify all structural encroachments falling within the designated right of way. In accordance with these findings, formal notices were served earlier to roughly 250 to 260 homeowners and commercial property owners, directing them to remove unauthorized portions within seven days.

## Trader Resentment And Demands For Financial Compensation
The arrival of demolition equipment prompted strong discontent among affected residents and local business owners. Many individuals face the prospect of losing entire houses and commercial outlets situated completely within the marked road alignment. Affected shopkeepers and residents gathered at the site to voice their opposition, asserting that adequate monetary compensation must be granted before their properties are razed. Despite the vocal resistance from traders demanding fair restitution, enforcement squads continued structural removal while maintaining tight security cordons to avert escalating confrontations.

## Impending Court Compliance Deadline Accelerates Action
The swift escalation of the demolition drive is closely linked to an impending legal deadline. The development authority is scheduled to submit a formal compliance report regarding the matter in court on 6 October. With merely a day left before presenting the update, officials accelerated efforts to clear all marked obstacles and secure the mandated road width. As the civic body pushes forward to meet court expectations and traders remain steadfast on compensation, the corridor between Sodala and Gurjar Ki Thadi remains charged with tension.

## What this means for you
The ongoing clearance drive and trader demonstrations along New Sanganer Road present immediate transit hurdles and commercial disruption.

- **Daily Commuters:** Structural dismantling and debris clearance between Sodala intersection and Gurjar Ki Thadi may severely slow down traffic. Motorists heading through this stretch should consider using alternate connecting roads to bypass congestion.
- **Commercial Property Owners:** Business operations have come to a standstill for over 250 shopkeepers whose premises fall within the road boundary. Traders face direct financial distress while continuing to seek financial relief from the civic body.
- **Jaipur Residents At Large:** Expanding the corridor to 160 feet will ultimately alleviate chronic traffic snarls on one of the city's key routes. However, transit delays and airborne dust will persist until development work concludes.
- **Impact On Homeowners:** Residents whose residential units sit within the demarcation line face immediate housing displacement challenges. Affected families will need to secure alternative accommodations following structural removals.

## Why this happened
The enforcement drive was launched to comply with court directives within a strict timeframe and eliminate bottlenecks along the route.

- **Judicial Compliance Deadline:** The development authority faces a mandatory court appearance on 6 October to submit its status report. This pending date prompted rapid mobilization of heavy machinery to clear the right of way.
- **Discrepancy In Road Width:** The planned design requires a 160 foot wide corridor, whereas the existing roadway spans only 100 to 120 feet. Expanding the bottleneck required clearing structures encroaching onto the designated corridor.
- **Expiry Of Prior Notice Period:** Civic officials had previously demarcated the boundary and issued seven-day evacuation notices to roughly 250 to 260 owners. Once the statutory notice duration lapsed, physical removal began as scheduled.
- **Absence Of Compensation Accord:** Shopkeepers contend that demolitions began without a formal restitution arrangement for their livelihoods, leading to organized roadside resistance.

## Questions & Answers

### 1. Which section of New Sanganer Road is undergoing the demolition drive?
The clearance operation is being carried out along the stretch connecting the Sodala intersection to Gurjar Ki Thadi.

### 2. What is the targeted width for the widened road?
The authority aims to expand the road to 160 feet, up from its existing width of 100 to 120 feet.

### 3. How many properties were served eviction notices prior to the drive?
Approximately 250 to 260 residential and commercial properties received seven-day notices to clear the road alignment.

### 4. Why are local traders and residents protesting at the site?
Affected individuals are demanding fair monetary compensation for the properties and shops affected by the road widening.

### 5. Why was the clearance operation accelerated on Monday?
The development body must submit a compliance report to the court on 6 October, prompting swift execution ahead of the hearing.

---