Road sections and edges sank at several locations on the Ganga Expressway during the monsoon, with incidents reported in Unnao and Amroha. The Centre is now preparing changes to the rules for awarding highway contracts. The Ministry of Road Transport and Highways proposes to weigh a company’s record and delivery pace alongside its financial and technical capacity, instead of giving the lowest bid the dominant role.
The proposal would revise the model Request for Proposal used for Engineering, Procurement and Construction, or EPC, contracts. The current rules were issued in March 2019. The proposed amendments cover eligibility, joint ventures, performance security and the process that follows an ineligible bid. The stated aims are to improve construction quality and curb delays in projects.
Ongoing work would count toward eligibility
A company’s bid capacity, which determines whether it is eligible to bid, would be assessed differently. The existing approach used the company’s performance in its strongest financial year as a basis for evaluation. Under the proposal, the pace of work on current projects and the company’s performance rating would also carry weight.
That would make a contractor’s record on active work relevant to its ability to qualify for another project. A company’s financial figures would no longer be the only consideration described in the eligibility assessment; progress on current work would also matter. The article does not specify a particular rating threshold or a number of days of delay that would affect eligibility.
The proposed approach is intended to favour companies that deliver projects on time and perform well, while taking account of their financial and technical ability. Since the assessment would include ongoing projects, a company’s current pace of work could influence its capacity to bid for new contracts. The proposal describes this link but does not set out the detailed scoring formula.
Fewer companies in a joint venture
The ministry also proposes tighter conditions for joint ventures, or JVs. A maximum of two companies, rather than three, would be allowed to form a JV for one project. As a general rule, JVs would be permitted only for projects costing more than 1,000 crore rupees. The minimum stake required of the JV’s second company would also be raised or otherwise made stricter.
The proposed limit would reduce the number of partners, while the revised stake condition would make the second partner’s participation more substantial under the rules. The article does not state what the minimum stake would be. It specifies the proposed cap of two companies and the general cost threshold, without giving further details on how the stricter participation condition would be calculated.
Relevant experience for bridges and tunnels
Additional technical eligibility requirements are proposed for projects involving major bridges, special structures and tunnels. Companies seeking these contracts would need actual experience in the relevant type of construction. Experience with ordinary highway work alone would therefore not automatically meet the proposed requirement for every specialised project.
The proposal ties technical qualification to the kind of structure being built. It identifies major bridges, special structures and tunnels, but the article does not give a required number of completed projects, minimum experience period or project value. The stated condition is that a bidder must have real experience in the relevant construction work.
Security amount linked to company rating
Performance security would also be connected to a company’s rating. Under the proposal, companies may have to submit security equal to 3 to 5 per cent of their bid price. The required amount would thus depend on the rating and the value of the bid. The ministry would also allow security documents to be submitted electronically.
The article does not specify which rating corresponds to which percentage in the 3 to 5 per cent range. Still, the proposed security is a financial requirement tied to the bid value, with the company’s rating also shaping the assessment. Electronic submission would provide an online option for the documents, while the percentage range remains the one stated in the proposal.
Disclosure of disputes and performance issues
The number of criteria used to assess poor company performance would be cut from 20 to 7. Clear thresholds and an evaluation period would be set for those criteria. The proposal also seeks stronger provisions for serious technical failures, termination of a contract, blacklisting a company and insolvency.
To increase transparency, companies would have to disclose disputes, court cases, arbitration proceedings and punitive action involving them. They would need to keep this information updated during the bidding process. That would make current cases and actions part of the information available for evaluation, while the revised framework would use fewer criteria with defined thresholds and assessment periods.
Fresh tender possible if the lowest bidder is ineligible
Under the current process, if the lowest bidder is found ineligible, the second-lowest and then the third-lowest bidder can receive counter-offers in sequence. The proposed revision would remove that provision. If the lowest bidder does not qualify, the authority could cancel the entire bidding process and invite fresh tenders.
The change would replace the sequence of counter-offers to the next bidders with the option of restarting the tender. The article does not set out a separate deadline for a fresh invitation or detail other circumstances in which the authority would use this option. It describes the power as one available when the lowest bidder is found ineligible.
Changes across the RFP document
The proposed amendments cover six sections of the RFP, 12 appendices and nine annexures under Appendix-IA. Three new formats would also be added. The revisions would therefore touch several parts of the tender document, as well as the forms used alongside it, in addition to changing eligibility and bid procedure rules.
The ministry expects the changes to encourage capable companies with stronger performance records to take up highway construction work. It also says the revisions are intended to strengthen construction quality, accountability and transparency in tendering. The article does not state when the proposed amendments would take effect or describe the next step in their approval.