Nagaland Pushes for Rapid Finish of Mon Medical College as 65 Percent Civil Works ConcludeNagaland
1 Oct 2026, 4:20 pm (1 hour ago)· 0

Nagaland Pushes for Rapid Finish of Mon Medical College as 65 Percent Civil Works Conclude

Nagaland Health and Family Welfare Minister P Paiwang Konyak has directed executing agencies to speed up construction at Mon Medical College, where roughly 65 percent of work stands completed.

The government of Nagaland has stepped up efforts to expedite the remaining developmental phases of Mon Medical College as the seasonal construction window opens. Health and Family Welfare Minister P Paiwang Konyak instructed the executing agency to prevent any additional hold-ups and push forward with site operations. The minister conducted a comprehensive ground inspection across the campus in Mon district on Wednesday alongside senior administrative and medical personnel.

Inspection of Key Campus Infrastructure

The visiting delegation comprised Commissioner and Secretary for Health and Family Welfare Kevileno Angami, Department Secretary S Tainiu Khiam, Principal Director Dr Keveduyi Theyo, Joint Director Dr Kika Longkumer, and Medical Engineering Division Executive Engineer Er Therouovituo Pienyu. The inspection covered essential campus components, reviewing planned residential quarters, academic facilities, a helipad, and local water sourcing infrastructure.

Also read

Upgrading the District Hospital for Clinical Training

During the assessment, Paiwang highlighted that the local District Hospital serves as the designated teaching facility for the upcoming medical college. He maintained that the hospital must be fully outfitted with every requisite clinical service, medical amenity, and technical system standard to a functional teaching institution. Furthermore, the minister assured departmental staff and contractors of comprehensive state government backing to guarantee that deadlines are met.

Weather Disruptions and Timeline Adjustments

Executive Engineer Theruovituo Pienyu briefed the visiting panel on physical progress, confirming that approximately 65 percent of the overall installation has been executed. Detailing past obstacles, he explained that severe weather spells, restricted working months, and frequent landslides across the district had severely hampered the logistical transit of raw materials to the site. In light of these geographical hurdles, the contracting firm has formally sought an extension of around eight months to wrap up all pending assignments.

Community Engagement and Stakeholder Consultations

The monitoring team expressed satisfaction regarding structural craftsmanship and general operational momentum. Following the walk-through, the minister convened a consultative dialogue featuring members of the Mon Village Council, local property owners, and engineering authorities to iron out outstanding logistical priorities and maintain steady site progress.

Questions & Answers

What proportion of Mon Medical College has been constructed so far?
According to the executive engineer, approximately 65 percent of the project has been completed.
What factors caused past delays in the construction timeline?
Progress was impeded by a short construction season, harsh weather, and landslides that disrupted the transport of building materials.
How much additional time has the building contractor requested?
The executing contractor has asked for an extension of around eight months to finish the remaining assignments.
Which facility is designated as the teaching hospital for the medical college?
The District Hospital has been designated as the teaching hospital and will be equipped with required institutional healthcare infrastructure.
Who participated in the on-site inspection visit?
Health Minister P Paiwang Konyak was joined by Commissioner and Secretary Kevileno Angami, Secretary S Tainiu Khiam, and senior departmental directors and engineers.

Comments 2

Karan Malhotra@karan-malhotra·19m ago

A medical college is great, but was the eight-month delay purely because of the weather or contractor negligence?

Ravikash Gupta@ravikash·18m ago

Karan, weather issues are fine, but do they really need eight more months, or is the contractor just dragging their feet?

Citizen journalism

Become a TrendKia journalist

Voice of the people

Share news, photos and videos from your area with TrendKia and let your voice reach the nation. Every citizen a journalist.

Join now
CH 01 LIVE
TrendKia TV ON AIR
Chamar no WhatsApp