Rajasthan Gets 600MW Power Boost For Diwali As Kalisindh Thermal Plant Unit Resumes Production After Two MonthsRajasthan
7 Nov 2026, 5:52 pm (6 hours ago)· 0

Rajasthan Gets 600MW Power Boost For Diwali As Kalisindh Thermal Plant Unit Resumes Production After Two Months

The stalled unit of the Kalisindh thermal power plant in Jhalawar has resumed power generation just ahead of Diwali, adding 600MW of electricity to Rajasthan's grid after being shut for two months due to technical faults.

Electricity consumers across Rajasthan have received a major relief ahead of the Diwali festival as a closed unit of the Kalisindh thermal power plant, located in the Jhalrapatan area of Jhalawar district, has officially resumed operations after a gap of two months. The restart of power generation from this unit right before Diwali has paved the way for an additional 600 megawatts of electricity supply to the state. This timely revival is expected to significantly strengthen the power distribution network across the region during the peak festive period when energy demands traditionally skyrocket.

The Steam Line Blast And Two-Month Shutdown

Operations at the facility had come to a halt approximately two months ago when a sudden blast occurred in the steam line of the first unit at the Kalisindh thermal power plant. This unexpected technical malfunction forced authorities to shut down the machinery immediately. Subsequently, the downtime was utilized to carry out comprehensive annual maintenance and necessary engineering repairs. For weeks, anticipation had been building regarding the reactivation of the stalled infrastructure. Following the successful resolution of all technical bottlenecks and completion of critical upkeep, the unit was brought back online just one day prior to Diwali.

Also read

Both Units Operating At Full Capacity

The Kalisindh facility houses two massive generating units, each boasting a capacity of 600 megawatts, bringing the plant's total combined generation potential to 1,200 megawatts. Ever since the first unit suffered its mechanical failure, plant operators had been forced to rely solely on the second unit to maintain continuous power generation. Consequently, the facility was operating well below its maximum potential, failing to utilize its full infrastructure capability. With the first unit now fully restored and functioning alongside the second, electricity production from both operational arms has normalized completely.

Easing Power Demands During The Festive Season

Given the surging demand for electricity throughout the festive season, the return of the dormant Kalisindh unit is being hailed as a crucial development for the state. During Diwali celebrations, consumption spikes dramatically across residential neighborhoods, bustling commercial markets, and industrial corridors alike. The infusion of an extra 600 megawatts provides a vital cushion to the state's electricity grid. Authorities are optimistic that the simultaneous functioning of both units will successfully mitigate any risks of power shortages during the festivities, ensuring that consumers enjoy reliable and uninterrupted power supply.

Questions & Answers

Where is the Kalisindh thermal power plant located?
The plant is situated in the Jhalrapatan area of Jhalawar district.
How much additional power has been added to the grid?
The restarted unit has cleared the way for an additional 600 megawatts of electricity for the state.
Why was the power unit shut down?
The unit had to be closed about two months ago due to a blast in its steam line and subsequent technical faults.
What is the total generation capacity of the plant?
The plant features two units of 600MW each, bringing its total combined generation capacity to 1,200 megawatts.
When was the unit brought back online?
The closed unit was successfully restarted just one day prior to the Diwali festival.

Comments 0

No comments yet — be the first.

Citizen journalism

Become a TrendKia journalist

Voice of the people

Share news, photos and videos from your area with TrendKia and let your voice reach the nation. Every citizen a journalist.

Join now
CH 01 LIVE
TrendKia TV ON AIR
Chamar no WhatsApp