Demolition Worries Mount in Dehradun as 13-km Elevated Highway Project Enters Land Acquisition Phase

Over 200 houses across 15 localities face partial or total demolition as NHAI begins marking land for a ₹2,000-crore elevated corridor between Asharodi and Mianwala in Dehradun.

A major transportation infrastructure project aimed at decongesting Uttarakhand's provisional capital has triggered widespread panic among hundreds of urban households. Preliminary surveys and ground marking have officially commenced for a planned elevated highway connecting Asharodi to Mianwala. Survey teams have started painting red markings on residential structures and commercial establishments situated along the proposed alignment. Initial estimates indicate that more than 200 properties spread over 15 neighborhoods could be impacted by the acquisition drive. While certain buildings are slated for complete demolition, others are expected to suffer structural slicing, sparking immediate pushback and organized protests from resident communities.

Tackling Chronic Bottlenecks Along the Southern Corridor

The newly developed Delhi-Dehradun Expressway culminates near the entry point of Asharodi. Beyond that threshold, arriving motorists merge into dense metropolitan stretches choked with local settlements and frequent intersections. The corridor connecting the Rispana junction to Jogiwala routinely experiences gridlock, creating severe transit delays across peak commuter hours. To circumvent these bottlenecks, the National Highways Authority of India (NHAI) designed a 13-kilometer elevated route linking Asharodi directly with Mianwala. The entire infrastructure undertaking is projected to cost around ₹2,000 crore. Notably, nearly half of this capital outlay, estimated at ₹1,000 crore, has been earmarked strictly for acquiring private plots and compensating affected owners. The Detailed Project Report (DPR) outlining these engineering specifics has already been submitted to the central government for final evaluation.

Also read

Neighborhoods Organize Over Loss of Dwellings

Tensions have escalated steadily since official survey parties began stamping buildings with red markers. Apprehensive over the imminent destruction of their homes, affected residents have formed a dedicated action committee to collectively lobby against the project. The committee has formally demanded the revocation of the land acquisition notification, arguing that the displacement will shatter the livelihoods of numerous families. Demands have also surfaced calling for a complete shelving or realignment of the elevated corridor. Officials point out, however, that the exact count of entirely demolished versus partially impacted buildings will only become definite once final surveying and legal demarcation are wrapped up.

Footprint Covers Private Properties Across Fifteen Localities

The geographic scope of the acquisition effort spans a broad swath of urban pockets. Properties are being surveyed in Majra, Dehrakhas, Brahmanwala, Sewla Khurd, Badripur, Majrimafi, Mohabbewala, Mohkampur Khurd, Kargi Grant, Shahnagar, Ajabpur Kalan, Ajabpur Khurd, Chakshahnagar, Chak Ajabpur Khurd, and Taluk Dehradun. Engineering assessments show that a 23-meter-wide clearance is necessary along the five-kilometer section between Ajabpur and Mianwala. This designated stretch accommodates numerous private plots, multi-story residences, and retail shops, alongside select parcels owned by the railways and the state government.

Current Status and Pending Clearances

Addressing the ongoing groundwork, NHAI Project Director Saurabh Singh confirmed that the land procurement process for the elevated corridor has been initiated and field demarcations are currently underway. Singh also noted that the DPR remains under review with central authorities. While urban planners maintain that the elevated expressway will fundamentally ease traffic pressure across Dehradun, affected property owners remain focused on the legal contours of acquisition, financial compensation packages, and upcoming administrative directives.

Questions & Answers

What is the total length of the proposed elevated road in Dehradun?
The elevated highway will measure approximately 13 kilometers in length, stretching between Asharodi and Mianwala.
What is the estimated cost of this highway project?
The project is estimated to cost around ₹2,000 crore, with approximately ₹1,000 crore allocated for land acquisition.
How many houses are expected to be affected by the road construction?
Initial estimates indicate that more than 200 houses across 15 localities may face full or partial demolition.
How much land width is needed between Ajabpur and Mianwala?
A 23-meter-wide clearance is required along the five-kilometer stretch between Ajabpur and Mianwala.
Why are local residents protesting against the elevated highway?
Fearing displacement and structural loss following red markings on their properties, residents formed a committee seeking cancellation of the acquisition notice.
Which major areas fall under the proposed land acquisition zone?
The footprint covers 15 localities including Majra, Dehrakhas, Brahmanwala, Sewla Khurd, Badripur, Majrimafi, Mohabbewala, Kargi Grant, and Ajabpur Kalan.

Comments 0

No comments yet — be the first.

Citizen journalism

Become a TrendKia journalist

Voice of the people

Share news, photos and videos from your area with TrendKia and let your voice reach the nation. Every citizen a journalist.

Join now
CH 01 LIVE
TrendKia TV ON AIR
Chamar no WhatsApp